| No | Project | Client | Scope of Work | Period | Hit |
|---|---|---|---|---|---|
| 15 | HCP No.2 BTX Flare & PSV Project | HD HYUNDAI HEAVY INDUSTRIES |
- Process Simulation - Flare Load Analyzing - Network Calculation - Flare System Purchasing |
2011.04 ~ 2011.07 | 230 |
| 14 | Flare System Capacity Assessment Procurement Project | Samsung BP Chemical |
- Flare Load Analyzing - Network Calculation - PSV Sizing |
2011.03 ~ 2011.07 | 218 |
| 13 | Polymer Pilot Plant Flare | Samsung Petrochemical |
- Flare Load Analyzing - Network Calculation - PSV Sizing |
2011.03 ~ 2011.04 | 211 |
| 12 | YERP PSV Load Calculation | SK E&C |
- Flare Load Reanalyzing - Network Calculation - PSV Sizing |
2011.02 ~ 2011.07 | 221 |
| 11 | No.2 FCC Flare System Study Project | SK E&C |
- PSV Load Evaluation - Flare Load Analyzing - Flare Header Network Calculation |
2010.10 ~ 2010.11 | 224 |
| 10 | Synthetic Rubber Plant Basic Design and Flare Load Analysis Project | LG Chem |
- Flare Load Analyzing - Flare Header Network Calculation |
2009.08 ~ 2010.12 | 238 |
| 9 | IGD Flare Gas Project | HD HYUNDAI HEAVY INDUSTRIES |
- Flare System Basic Design (Network Calculation, etc.) - PSV Sizing |
2009.11 ~ 2010.09 | 223 |
| 8 | LG Chemical Flare | LG Chem |
- Process Simulation - Flare Load Reanalyzing - Network Calculation - Trouble shooting for existing Flare System |
2008.02 ~ 2008.05 / 2009.0. ~ 2009.05 (2 times) | 220 |
| 7 | KTIA Flare (USA) | Crown Asphalt Ridge, L.L.C. USA |
- Flare Load Analyzing - Network Calculation |
2009.07 ~ 2009.12 | 216 |
| 6 | GS Caltex No.4 CDU Revamping | GS E&C |
- Unit Load recalculation - Network Calculation |
2008.01 ~ 2009.05 | 204 |